- Home
- City Government
- Departments A-G
- Engineering Department
- Road Work Updates
Road Work Updates
Special Notices
We will try to keep this site up to date and accurate as possible. Changes to the schedules may occur without notice. Please try to avoid these areas during construction or plan on delays when navigating through the work zones. Paving dates are subject to change due to weather conditions.
Current Construction Schedule
Roadway | Activities and Duration |
---|---|
Armanella Street | Final paving scheduled for the week beginning April 19th. Project scheduled to end soon thereafter. |
Baskin Drive | Final paving scheduled for April 19th. Project scheduled to end soon thereafter. |
Burnett Road | Pavement milling on April 15th, final paving scheduled for April 20th. Project to be completed by the end of April 2021. |
Fuller Road | Project has begun with completion date of August 2023. Utility work is currently underway. (This is a MassDOT project.) |
New Lombard Road |
Road will be closed to through traffic during work hours beginning on April 19th. Local traffic only will be allowed during these hours. Through traffic will be allowed after weekday work hours and on the weekends. Project completion is scheduled by June 1st. |
Massachusetts Turnpike (I90) | The MassDOT will begin a project in May 2021 to realign the entrance and exit ramps at (former) Exit 6 and involves work along Burnett Road / I291 and the ramp to Fuller Road. (This is a MassDOT project.) |
Installation of driveway aprons and sidewalks scheduled for the week of 5/23/16 |
Installation of water main scheduled for 7/27- 8/5/16 |
Installation of water main scheduled for 7/27- 8/5/16 |
Reclamation and grading of roadway 8/2- 8/12 |
Reclamation and grading of roadway 8/2- 8/12 |
Reclaim/remove asphalt 9/6- 9/8 |
Fine grading 5/29- 6/4 Paving 6/4- 6/6 |
Fine grading 5/29- 6/4 Paving 6/4- 6/6 |
Grading of roadway 9/4- 9/14 |
Grading of roadway 9/4- 9/14 |
Fine grading 3/4- 3/5 Installation of dense grade gravel 3/8 Paving 3/9 |
Adjustment of structures 4/8- 4/11 Reclaim of roadway 4/12- 4/15 |
Driveways, sidewalks 6/3- 6/14 Paving 6/4- 6/5 |
Driveways, sidewalks 6/10- 6/21 Paving 6/10- 6/11 |
Driveways, sidewalks 6/24- 7/12 No construction week of 7/1 |
- Structure adjustment 3/27 - Sprinkler repair scheduled for Saturday April 6th |
- Structure adjustment 3/27 - Sprinkler repair scheduled for Saturday April 6th |
Contact Us
-
Douglas E. Ellis, P.E.
City Engineer
Email
Engineering Department
115 Baskin Drive
Chicopee, MA 01020
Phone: 413-594-3416
Fax: 413-594-3441
Staff Directory