1992 |
Construction of the Corrosion Control Building
|
1991 |
Construction of the Royal Street Elevated Storage Tank
|
1950 |
Completion of the Chicopee Valley Aqueduct Connecting Distribution System to the Quebin Reservoir and Completion of the New Treatment Plant at the Chicopee-Ludlow Line
|
1942 |
Began Laying 30 Feet Main Connecting Cooley Brook and Supply System of City of Springfield
|
1932 |
Erection of Treatment Works Facility Completed
|
1927 |
New Cooley Brook Dam and Reservoir Built
|
1914 |
Cooley Brook Dam Rebuilt After Washout in 1913
|
1893 |
City of Chicopee Purchases Water Rights and Property From the Chicopee Water Company and City Council Approves Construction of the Cooley Brook System
|
1892 |
City of Chicopee Purchases Water Rights and Property From the Willimansett Water Company
|
1882 |
Willimansett Water Company Incorporated
|
1877 |
Chicopee Water Company Incorporated
|
1867 |
Chicopee Central Fire District Began Laying Mains and Hydrants
|
1848 |
Chicopee Central Fire District Organized and Chicopee Falls Fire District Also Organized
|
1836 |
Chicopee Predominantly got its Water From Wells and Springs
|